McEwen shares fell 20.8% after earnings as investors reacted to what management called an “unacceptable” quarter, with operational problems at Gold Bar, elevated costs at Fox and lower production and recoveries at San Jose. Management pointed to improvement in October, but those updates do not erase the weak quarter or the need to prove the fixes are durable.

Key takeaways
  • At Gold Bar, oversight and decision-making issues contributed to a difficult quarter; output improved late in September, and October was the mine’s highest-production month in 15 months.
  • Fox costs rose as development spending was concentrated in Q3 and the mill processed low-grade stockpiles; management said October costs returned within guidance.
  • At San Jose, heavy snowfall and excess moisture disrupted mill performance, prompting a shift to lower-grade sulfide stockpiles and contributing to lower production and recoveries.
  • The company expects the Stock Mine to begin contributing benefits from December and early next year; management cited an 8.5–9-year mine life, compared with a couple of years for Froome and Froome West.
  • For Los Azules, a final investment decision with full project financing is targeted for mid-2027; an updated feasibility study is in progress, with engineering work and EPCM bid evaluation underway.