WhiteFiber, Inc. Ordinary Shares

WhiteFiber, Inc. Ordinary Shares Earnings Recaps

WYFI Technology 2 recaps
Next earnings: March 25, 2027 (estimated) · full calendar
Q3 2026 Nov 12, 2026

White Fiber shares rose 9.0% after the company reported that all 40 MW at NC1 are operational and billing, alongside more than $700 million of new cloud-services contract value. The market appears to have focused on project completion and demand for 2027 capacity, despite delays in reaching full billing and execution and financing dependencies for future sites.

Key takeaways
  • NC1’s full 40 MW is now operational and billing; billing for the second 20-MW phase began November 9 after switchgear and commissioning delays. Management does not expect late-delivery penalties.
  • NC1 development costs are expected to finish just below $9 million per gross MW, within the original $7 million–$9 million range, excluding site acquisition costs and net of customer-funded nonrecurring costs.
  • The company signed more than $700 million in new cloud-services contract value since its prior call, including its first capital-light managed-services agreements.
  • White Fiber completed a $60 million acquisition of NC2 and NC3, with at least 60 MW of initial gross utility capacity; it is targeting initial capacity in late 2027, subject to power, customer commitments, financing, and approvals.
  • Advanced discussions cover about 105 MW of North Carolina capacity for 2027, including 45 MW of potential NC1 expansion and 60 MW at NC2 and NC3. Management says current proposals’ pricing and terms would more than offset higher development costs, but it has not yet committed to those projects.
Q2 2026 Aug 14, 2026

White Fiber shares jumped 16.5% after earnings, reflecting investor optimism around the initial revenue start and full deployment progress at NC1, as well as positive developments in the company’s development pipeline and customer engagement.

Key takeaways
  • NC1 has transitioned into active customer deployment with initial billing commenced for approximately 20 megawatts; full 40-megawatt contracted load expected to reach full run rate billing by end of August.
  • Previous equipment delivery and commissioning delays were resolved, and phased turnover is progressing steadily in close coordination with customers and vendors.
  • The company is advancing plans to expand NC1 capacity beyond 40 megawatts, with Duke Energy expected to confirm delivery schedules for an additional 45 megawatts and discussions ongoing for a potential further 200-megawatt expansion.
  • Decision made to move forward with approximately 5 megawatts of capacity development at the NTL2 Canadian site, supported by ongoing customer discussions and evaluation of deployment approaches.
  • Other Canadian assets like MTL1 and MTL3 remain stable with ongoing customer renewals and expansion efforts underway; demand for power-ready AI infrastructure remains strong, especially for 2027 deployments.